Oracle 1Z0-1075-24 Exam - Free questions
Certification Provider:
Oracle
Exam Name:
Oracle Manufacturing Cloud 2024 Implementation Professional
Exam Version:
1Z0-1075-24
1Z0-1075-24 Free questions:
Here you can find Oracle Manufacturing Cloud 2024 Implementation Professional exam free sample questions which will help you to prepare for your upcoming certification test. These questions will give you an idea of what to expect on the exam and help you review the 1Z0-1075-24study material.
These 1Z0-1075-24 questions are updated regularly, so you can be confident that you're studying with the most up-to-date information available. We also provide answer keys so that students can check their work.
Additionally, going through Oracle Manufacturing Cloud 2024 Implementation Professional practice questions can help you identify any areas where you need more review. Taking advantage of our 1Z0-1075-24 demo questions is a great way to set yourself up for success on the real thing.
Question No. 1) Identify four parameters that are considered in the calculation of manufacturing lead time in Oracle Manufacturing Cloud.
A) Resource calendars of the work centers involved
B) The primary work definition of the item
C) The lot size of the item
D) The shifts are defined in the plant calendar
E) Plant calendar exceptions
F) Resource calendar exceptions
Question No. 2) During a Manufacturing Cloud implementation, the Production Supervisor wants to close the work orders for last month and wants to make sure that the work orders include the correct cost. Identify the approach to be taken by the Production Supervisor.
A) The Production Supervisor need not include cost variances while costing last month’s workorders because those can be applied directly in subledger accounting.
B) The Production Supervisor needs to include all costs and variances in last month’s work orders and close them; however, the work orders where updates are expected, should not be closed.
C) The Production Supervisor should make sure that all costs are included while closing last month’s work orders; however, variances can be included after closing the work orders.
D) Work order costs can be updated anytime regardless of the status of the work order.
Question No. 3) Your customer plans to use Oracle Representational State Transfer (REST) API with Oracle Supply Chain Management Cloud (Oracle SCM Cloud) to support integration requirements. Identify four REST resources and the corresponding HTTP action available with Manufacturing Cloud.
A) Work Order Status GET method
B) Work Orders GET method
C) Work Order Status POST method
D) Work Orders PATCH method
E) Resource transaction POST method
F) Resource transaction GET method
Question No. 4) In a Manufacturing Cloud post production support environment, a user wants to update some of the operations in the work orders by using the Midpoint Scheduling feature. However, the user is unable to update any of the orders. Identify two reasons.
A) The work order operations do not have operations start or completion date.
B) The scheduled resources are not part of the organization selected by the user.
C) None of the operations include scheduled resources.
D) The operations are missing sequence.
Question No. 5) A production Supervisor has noticed that Work Orders created manually are overwritten by the plan runs executed by Planning Central. After discussing this issue with the Planner, two actions are recommended to prevent the Work Orders from being overwritten by plan runs. Identify the two recommendations.
A) Update Supply Plan Options, Overwrite Firm Planned Orders = None.
B) Update Firm flag in the Details region of the Edit Work Definition page.
C) Update Firm flag in the Details region of the Edit Work Definition Names page.
D) Update Firm flag in the Details region of the Edit Work Order page.
Question No. 6) The Plant Manager informs you that they have bought several machines for their manufacturing plant ABC. The plant has been set up with a separate cost element set ABC in Manufacturing Cloud. You are requested to configure these machines in such a way that those are costed to the work order for which operations are performed on these machines. Identify the correct setup that you will advise to the Plant Manager.
A) Set up the machines as cost element type of “Resource” by selecting Cost Element set ABC.
B) Set up the machines as cost element type of “Overhead” by selecting Cost Element set ABC.
C) Set up the machines as cost element type of “Overhead” by selecting Cost Element set Common.
D) Set up the machines as cost element type of “Resource” by selecting Cost Element set Common.
Question No. 7) A manufacturing cloud user wants to print information available in the work order in PDF. Identify the three reports that the user can print directly from the work order screen using the Print PDF action.
A) Work Order Traveler
B) Resource List
C) Print Labels
D) Print Component List
E) Bill of material
Question No. 8) Work order costs are computed based on material and resource transactions reported and the cost method of the product. In a manufacturing plant, the production operator has completed a work order WO-001 ensuring proper materials and resource transactions. The materials are costed and resources are defined with rates. A cost accountant has created cost accounting distributions. Upon reviewing the accounting distributions of the work order WO-001, resources charged to the work order are missing. Identify the Concurrent Request that needs to be submitted to transfer resource charges to cost accounting.
A) Create accounting
B) Transfer Transactions from Production to Costing
C) Transfer Transactions from Inventory to Costing
D) Transfer Costs to Cost Management
Question No. 9) In what three ways can you set the over completion tolerance for a subcomponent yield, so the job order can report the excess production completion?
A) Over completion Tolerance Type = Amount, value > 0
B) Over completion Tolerance Type = Amount, value = 0
C) Over completion Tolerance Type = Percentage, value = 100
D) Over completion Tolerance Type = Percentage, value > 0
E) Over completion Tolerance Type = Percentage, value = 0
Question No. 10) A user wants to transfer the work order status updates and resource transaction data for costed resources to Cost Management. Which scheduled process should you run to achieve this requirement?
A) Transfer Cost to Cost Management
B) Transfer Transactions to Costing
C) Transfer Ledger Balances
D) Transfer General Ledger Balances to Balance Cubes
Question No. 11) A Production Supervisor queries a Work Order (WO-1025) from the manage Work Orders page. On the Entering Edit Work Order: WO-1025 page, he finds General Information, Operations and History tab, but not the Reservations tab. Identify the two reasons that can cause the Reservations tab not to be displayed.
A) Work Order (WO-1025) is not a Configured item Work Order.
B) Work Order (WO-1025) is not a Back-to-Back Work Order.
C) Work Order (WO-1025) is not a Drop-ShipWork Order.
D) Work Order (WO-1025) is not a Pick-to-order Work Order.
E) Work Order (WO-1025) is not a Plan-to-produce Work Order.
Question No. 12) A production Operator is executing work order in your plant. After completing move transactions, he notices that he has performed some incorrect move operations, including incorrect scrap and reject transactions. He is required to perform a reverse transaction to correct the errors. The operations are not count point enabled and not auto charged. Identify the four transactions to correct this situation.
A) Reverse from reject to ready.
B) Reverse from scrap to ready.
C) Reverse resources charged to a work order.
D) Reverse material issued to a work order.
E) Reverse at an operation.
F) Reverse the product at the last operation.
Question No. 13) In a manufacturing plant, two purchase components P1 and P2 and a resource R1 are required to assemble a product. The cost of the assembly is calculated by using the standard costing method. The work definition and resource rates of the assembly have been defined as required. A cost accountant is estimating cost of the assembly, analyzing rolled-up costs before finally publishing estimates as frozen standards to cost accounting by using a cost planning scenario. While reviewing rolled up costs, the extended costs of purchase components are not included in a rolled-up scenario. Identify the reason.
A) Purchase components P1 and P2 are not associated with Material cost plan of the cost planning scenario.
B) Costs for purchase components P1and P2 are not defined in cost accounting.
C) Create Accounting was not initiated.
D) Create Accounting Distributions was not initiated.
Question No. 14) Which two steps should you use to create a new Oracle Transactional Business Intelligence report in the Manufacturing Cloud?
A) Use ibots to create the report.
B) Use Business Intelligence answers to create the report.
C) Use the Manufacturing subject area to select the report columns and create the report.
D) Use Business Intelligence publisher to create a template and use that template to create the report.
Question No. 15) A production operator needs to review the materials issued, resources charged, and operations performed for a job that was executed in the previous shift. Identify the task the operator has to select to review all the transactions in a single place for both Work Order and Order less execution.
A) Manage Work Orders
B) Review Dispatch List
C) Report Resource, Material and Operation Transactions
D) Review Production Transaction History
Question No. 16) In a manufacturing cloud implementation, production operators want to perform work order updates using Dispatch List. Identify two tasks that the Dispatch List allows the production users to perform.
A) Report Component Returns
B) Report Resource Transactions
C) Report Receipts
D) Report Material Transactions by Quantity and Serial Number
E) Report Cost Transactions
Question No. 17) A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts. Determine the available capacity of the resource R1 for that week.
A) 78 hours
B) 76 hours
C) 60 hours
D) 70 hours
Question No. 18) A Production operator in your company is required to report production activities, such as completing or scrapping production units, by referencing a work definition without creating work orders. Identify the manufacturing transaction that a production operator can perform for reporting such activities.
A) Order less Transactions
B) Operation Transactions
C) Resource Transactions
D) Movement request
E) Material Transactions
Question No. 19) In your customer’s manufacturing facility, different types of Movement Requests are created. Key manufacturing components are issued to the work orders form the manufacturing sub inventory. The manufacturing sub inventory receives its supplies form the Warehouse sub inventory through automatically created Movement Requests. Which type of Movement Requests should you use to fill the manufacturing sub inventory form the Warehouse sub inventory?
A) Batch Wave Movement Requests
B) Pick Wave Movement Requests
C) Replenishment Requests
D) Requisition Movement Requests
Question No. 20) Identify three types of Item Quantities displayed in the Work Order History tab.
A) Scrapped Quantity
B) In Process Quantity
C) Remaining Quantity
D) Total Quantity
E) Completed Quantity
Question No. 21) You can generate and manage work order exceptions in Oracle Manufacturing Cloud. Which users can report production exception and who gets notified after an exception is raised?
A) The Production Operator can report and exception and the application generates a notification that is sent to all users who have access to the manufacturing plant.
B) The Production Operator can report an exception and the application generates a notification that is sent to all users with the role of production supervisor who have access to the manufacturing plant.
C) The Production Operator or Manufacturing Engineer can report an exception and notifies the production supervisor using Oracle Social Network since there is no system generated notification.
D) The Production Operator can report an exception and notifies the production supervisor using Oracle Social Network since there is no system-generated notification.
Question No. 22) You have been asked to set up cost estimates for 10 different purchased items. Which two steps could be used to accomplish this task?
A) Use the Mass Edit functionality.
B) Run the ESS process “Update Item Cost Estimate”.
C) Enter cost estimates directly into UI.
D) Call web service.
E) Import spreadsheet.
Question No. 23) In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required. A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting. Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
A) Publish cost planning scenario to Accounting.
B) Build cost planning scenario and perform cost roll up.
C) Create Accounting Distributions.
D) Transfer transactions from production to Costing.
E) Define accost planning scenario with Material, Resource, Overhead cost plans, and work definition.
F) Transfer Transactions from Inventory to Costing.
Question No. 24) Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM) and Order promising (GOP), which must be set to process the with Back-to-Back order Make Supply Order, for a no stocked item.
A) Set the no stocked item to be back-to-back enabled in Product Information Management (PIM).
B) Set the global sourcing rule in GOP to determine supply creation option as Make.
C) Set a local sourcing rule in GOP to determine supply creation option as Make.
D) Create Supply Order Orchestration Defaulting and Enrichment Rule for the no stocked item.
E) Create Supply Chain Orchestration Supply Execution Document Creation Rule for the no stocked item.
Question No. 25) Identify the three sources from which supply chain orchestration (SCO) can create the work orders.
A) Order Management
B) Quality
C) Inventory Min-Max Planning
D) Procurement
E) Planning